Complete refurbishment of 2 classrooms including floor tiling, ceiling boards and painting. Tiling of the classroom veranda. Construction of a ramp and new steps to make the classrooms more accessible. Creation of a 'library' and purchase of class sets of text books. The addition of a double slide to the play ground and new shoes for all of the students
MAY 2025
Construction of furniture for the dining hall - tiling, painting and new cookers for the kitchen - extension of the perimeter wall - clearing, digging and planting crops for food
MAY 2024
Construction of the dining hall - additional perimeter walls added to prevent flooding
MAY 2023
Completion of the 2nd Double classroom - digging out the footings for the dining room
JULY 2022
Extension of the perimeter wall
MAY 2022
Start of construction of the second double classroom and kitchen